    Default Full/Incremental and retension

    I want to help set up the Amanda backup for weekly full, incremental, in the other day and retensão of two weeks.
    I have 6 tapes LTO3.

    This is possible?

    My setup so far is this:

    dumpcycle 1 weeks
    runspercycle 7 days
    tapecycle 6 tapes
    runtapes 1

    Tks!

  2. #2
    Join Date
    Nov 2007
    Location
    Sunnyvale, CA
    Posts
    59

    Default

    This isn't going to work...

    You either need to (a) add more tapes or (b) reduce your backup cycle. From the amanda.conf(5) man page:

    The number of tapes in rotation must be larger than the number of tapes required for a complete dump cycle (see the dumpcycle parameter).